Our contractor, Ev Air Tight, will be repairing and replacing capstones on planters and retaining walls throughout the cluster according to the following schedule:

Block 1 – Monday July 26 to Thursday August 19
Block 2 – Monday August 23 to Thursday September 16
Block 3 – Monday Sept 20 to Thursday September 30

​Please be advised that these dates may be moved up due to rain, and work would be conducted on Fridays if rain impacted progress during the week.

The contractor will set up a staging area with portable toilet in parking spaces ​122, 123, 124, 125, and 126 in the lot between Blocks 1 & 2. ​The board will inform the residents in Block 3 which parking spaces will be used as we get closer to the work dates.  The parking spaces used for the staging area will not be available for the duration of the project.  ​The workers will be placing plastic orange fencing around the work area.

Should you have any questions, please contact Silvia Merrill at silviamerrill@hickorycluster.org.